Timber Test Cells > Articles > Construction

Construction - July 11

All cells are now effectively complete. They are all insulated and lined and brickwork is finished. Final detailing is in progress with door trims, painting, and carpeting to come.

Monitoring equipment is now being prepared. Generally, sections of finishes are removable so that the sensors can be installed and tested, and replaced if necessary.


Finishing the brickwork on Cell 3
Finishing the brickwork on Cell 3

Setting the plaster cornice over the gap between the wall and ceiling linings
Setting the plaster cornice over the gap between the wall and ceiling linings

Each cell has an identical wall mounted heater.
Each cell has an identical wall mounted heater.

Electrical lines are surfaces mounted to minimise disruption to the insulation
Electrical lines are surfaces mounted to minimise disruption to the insulation



Construction complete - August 1
The construction of three thermal performance test cells at the University of Tasmania's Launceston campus is now complete. Special thanks for this go to postgraduate student, Mark Dewsbury and the builder cb&m design pty ltd, for mobilising the subcontractor team and supervising work.
Construction - July 8
Even allowing for some unkind winter weather, completion of the test cells is now in sight. They are all insulated and lined and cladding is well advanced.
Construction - June 26
Though three days were lost to rain, the frame for each building is in place, and the first cell has been wrapped.
Construction - June 15
With most services roughed in and the footings inspected, concreting has begun.
Preparation of footings - June 8
Treated posts are the footings for both Test Cells 1 and 2.
Construction - June 7
Construction is underway with the excavator preparing the foundations
Construction is now under way
The test cells are being built by contracted local builders using standard building material and construction systems. Construction began in early June and is scheduled to be completed by mid-July.







All participants...